78 Unit Contemporary Luxury Apartment Units
6,800 Sq. Ft. of Flex Commercial Space
Adjacent to the Bike Path Connected to Downtown
Desirable East San Luis Obispo Location
California’s Top Rated Small City
December 2017: Phase I financing complete
January 16, 2018: Site purchase transaction closed
April 11, 2018: First Planning Commission Meeting Held
July 11, 2018: Project Approved by the Planning Commission at second hearing
August 6th, 2018: First Architectural Review Committee Meeting
September 17th, 2018: Second Architectural Review Committee Meeting
September 17th, 2018: Project Approved
October 2018: Project Construction Working Drawings Commenced
Current: Site remains master leased and producing income for the Partnership.
January 22, 2019: Plans Submitted for the first round of Construction Document Plan-Check to the City of San Luis Obispo
April 1, 2019: Completed first round of Plan-Check with comments for a second resubmittal
May 2019 (est): First Plan-Check Resubmittal for Construction Documents
Spring 2019: Phase II financing to completed
August 2019: Commenced Construction